Case study · ExCeL London
New safety flooring across The Fox at ExCeL London in five nights, with no closures
A full flooring upgrade across the toilets, kitchen and preparation areas, carried out overnight across 5 nights, outside the venue's trading hours, so it stayed fully operational.

- Location
- ExCeL London
- Programme
- 5 nights, outside trading hours
- Closures
- None
The brief
The Fox needed a full flooring upgrade across its toilets, kitchen and preparation areas, without disrupting the venue.
What we did
- Installation of a DPM system
- Full latex preparation throughout
- Supply and installation of Altro safety flooring
- Works across all toilets, kitchen and preparation areas
How it was delivered
To avoid disrupting the venue, all works were carried out overnight, outside its trading hours, and the entire project was completed across just 5 nights with no closures required. Careful planning, coordination and efficient delivery allowed the venue to remain fully operational throughout.
Before and after


More photos


Need maintenance support?
Whether something has gone wrong today or you're planning maintenance across your sites, talk to us.
Ongoing maintenance and projects
Planned maintenance, refurbishment and construction.
Talk to our team